Basics

GModG timeline: what applies when for non-residential buildings

Updated 18 November 20266 min readSensMotion editorial team
In shortThe GModG (German Building Modernisation Act, Gebäudemodernisierungsgesetz) has applied since 29.07.2026, with further parts entering into force on 01.01.2027, 01.01.2028 and 01.01.2030. For lighting in non-residential buildings, three milestones matter most: 2027 (new reference building and new energy performance certificate), 31.12.2029 (automatic lighting control under Section 56(6)) and 2030/2033 (minimum energy performance under Section 40).
At a glance
First stage
29.07.2026, Article 1 (Art. 9(1), BGBl. 2026 I No. 226)
Second stage
01.01.2027, Articles 2 and 7 (Art. 9(2))
Third stage
01.01.2028, Article 3 (Art. 9(3))
Fourth stage
01.01.2030, Article 4 (Art. 9(4))
Lighting control
by 31.12.2029 (Section 56(6) GModG)
Minimum performance, existing buildings
from 01.01.2030 and 01.01.2033 (Section 40(2) GModG)

Why does the GModG have several start dates?

The GModG (sometimes also abbreviated GMG) was promulgated in the Federal Law Gazette, BGBl. 2026 I No. 226. Formally it is an amending act: it changes the former Building Energy Act (GEG) through several articles that take effect at different times. Article 9 sets the schedule:

(2) Die Artikel 2 und 7 treten am 1. Januar 2027 in Kraft. (3) Artikel 3 tritt am 1. Januar 2028 in Kraft. (4) Artikel 4 tritt am 1. Januar 2030 in Kraft.

Art. 9 Gesetz vom 23.07.2026 (BGBl. 2026 I Nr. 226)

In short: Articles 2 and 7 apply from 1 January 2027, Article 3 from 1 January 2028 and Article 4 from 1 January 2030. Everything else, above all Article 1 with the new Section 56, has applied since the day after promulgation, 29.07.2026. Articles 3 and 4 deal with zero-emission buildings; Article 7 amends the German act on e-mobility infrastructure in buildings (GEIG).

Does the GEG still apply?

Not under its old name. Article 1 No. 1 replaces the title of the act:

„Gesetz zur Einsparung von Energie und zur Modernisierung der Wärmeversorgung in Gebäuden (Gebäudemodernisierungsgesetz – GModG)“.

Art. 1 Nr. 1 Gesetz vom 23.07.2026 (BGBl. 2026 I Nr. 226)

Legally, the GModG is the renamed and revised GEG of 8 August 2020; "GEG" today usually means the version in force until 28.07.2026. Old rules now matter only through transitional provisions, for example for energy performance certificates issued before 01.01.2027 (Section 112) and for building automation installed up to three years before 01.01.2027 (Section 56(4)). What changed compared with the former Section 71a GEG is covered in GEG Section 71a vs. GModG Section 56.

Timeline 2026 to 2033 for non-residential buildings

The "Lighting" column shows whether a German rule directly affects lighting.

DateWhat appliesReferenceLighting
29.07.2026GModG in force, new Section 56: building automation and lighting control duties above 70 kWArt. 1, Art. 9(1)yes
01.01.2027Energy balance calculated to DIN/TS 18599: 2025-10 instead of DIN V 18599: 2018-09Sections 20, 21 (Art. 2)yes
01.01.2027New reference building: LED lighting instead of fluorescent; presence detectors, constant-light and daylight control and BACS class C remain (new zone numbers)Annex 2 Nos. 3.1, 3.2 and 9yes
01.01.2027Energy certificate: only the calculated (asset) rating on sale or letting, classes A–GSections 80, 86, Annex 10ayes
01.01.2027Inspections extended to ventilation systems above 70 kW, exemption with building automation under Section 56(2)Sections 74, 76indirect
01.01.2027Solar duty for new non-residential buildings above 250 m² and new public non-residential buildingsSection 106(2) No. 1no
01.01.2027Charging points where there are more than 20 parking spacesSection 10 GEIG (Art. 7)no
01.01.2028Zero-emission standard for new public buildings used by an authority, built-in lighting includedSection 10a (Art. 3)yes
01.01.2028Solar duty for certain existing buildings (public above 2,000 m², others above 500 m² on major alterations)Section 106(2) No. 2no
31.12.2028First inspection of air-conditioning systems above 12 kW that were over ten years old on 01.10.2023Section 76(1) sentence 3no
31.12.2029Building automation and automatic lighting control above 70 kWSection 56(1) and (6)yes
01.01.2030All new buildings zero-emission, built-in lighting includedSection 10 (Art. 4)yes
01.01.2030Existing buildings: primary energy demand at most 3.5 times the referenceSection 40(2) No. 1yes
01.01.2033Existing buildings: primary energy demand at most 2.95 times the referenceSection 40(2) No. 2yes

Further stages: solar duty for existing public buildings (2029, 2031) and first inspections of older ventilation systems within two, four or six years of 01.01.2027 (Section 76(1)).

What changes for lighting on 01.01.2027?

From 2027, lighting becomes more visible in the energy balance. The reference building for non-residential buildings will assume LEDs in LED luminaires instead of fluorescent lamps. Presence detectors in certain usage zones, constant-light control and daylight-dependent control of the type "dimmed, not switching off" were already part of the reference and remain so. The bar is therefore significantly lower. Zone details are explained in Reference building lighting from 2027.

For energy certificates, non-residential buildings that are sold or let will only receive the calculated, demand-based certificate (Section 80(3) sentence 2). The new efficiency class is derived from the ratio to the reference building (Section 86(4)), and lighting is part of the primary energy demand. A valid existing certificate may still be used (Section 80(3)); with the next one, lighting shows up in the class. See Energy certificate for non-residential buildings from 2027.

What must be in place by 31.12.2029?

Non-residential buildings whose heating, air-conditioning or combined system exceeds 70 kW rated output need two things by the end of 31.12.2029: building automation with the functions listed in Section 56(2), and automatic lighting control under Section 56(6). Both duties have been law since 29.07.2026; the deadline marks the end of the implementation period.

Section 108 sets no fine for Section 56(6), while breaches of Section 56(1) can cost up to €5,000. The lighting duty is binding nonetheless and can matter in leases, due diligence, ESG reporting and financing. Details: Section 56(6) GModG explained and Building automation under Section 56(1).

What follows in 2028, 2030 and 2033?

From 01.01.2028, new public non-residential buildings used by an authority must be zero-emission buildings (Section 10a); from 01.01.2030 all new buildings (Section 10 as amended by Article 4). In both cases the energy demand of built-in lighting in non-residential buildings counts expressly.

For existing non-residential buildings, Section 40 sets minimum values: from 01.01.2030 at most 3.5 times and from 01.01.2033 at most 2.95 times the primary energy demand of the reference building, lighting included. By our own derivation these values match the class thresholds G and F in Annex 10a. Many buildings are deemed compliant under Section 40(3), for example if built on or after 01.01.1996, supplied by district heating or heated mainly by heat pumps or biomass, and Section 40(4) exempts further cases such as listed buildings. For older buildings without these features the requirement stands, and lighting is a lever that does not touch the building envelope. See Minimum energy performance from 2030.

This overview is not legal advice; the statutory text is authoritative.

What should you plan for now?

  • By the end of 2026: check the rated output per system and whether your building exceeds 70 kW.
  • Before a sale or lease from 2027: allow for the demand-based certificate.
  • By 31.12.2029: plan, install and commission both systems, with a buffer for multiple sites.
  • For 2030 and 2033: check whether Section 40 applies or is deemed met.

Frequently asked questions

Since when has the GModG applied?

Since 29.07.2026, the day after promulgation in BGBl. 2026 I No. 226. Further parts follow on 01.01.2027, 01.01.2028 and 01.01.2030.

Does lighting control have to be installed by 2027?

No. The deadline under Section 56(6) ends on 31.12.2029. From 2027, however, lighting already affects the energy certificate and the reference building.

Is GMG the same as GModG?

Yes. The official abbreviation is GModG; GMG or GMod are also used for the former Gebäudeenergiegesetz.

Is the German deadline earlier than the EU deadline?

No. The EPBD has an earlier stage for buildings above 290 kW by 31.12.2027. Germany did not adopt it separately and requires lighting control above 70 kW by 31.12.2029.

Last reviewed: 18 November 2026. General information, not legal advice. The legal text is authoritative.

Getting started

From your question to a finished plan.

Free initial consultation, one contact person.

Send a photo of the driver labelWe check free of charge whether your luminaires can be retrofitted.
Add your floor planWe turn it into a 3D model with sensors and zones.
Planning and quoteYou see the result in 3D first, then you decide.