- Obligation
- automatic lighting control (Section 56(6) sentence 1 GModG)
- Deadline
- 31 December 2029 (Section 56(6) GModG)
- Scope
- non-residential buildings with a system above 70 kW rated output (Section 56(1) and (6) GModG)
- Default requirement
- appropriate zoning and occupancy detection (Section 56(6) sentence 2 GModG)
- Responsible party
- developer or owner (Section 8 GModG)
- Law
- GModG, BGBl. 2026 I No. 226, in force since 29 July 2026
Where does the obligation come from and who is covered?
The GModG replaced the former German Buildings Energy Act (GEG). It has been in force since 29 July 2026 (BGBl. 2026 I No. 226), with further parts following in 2027, 2028 and 2030. Among other things, it transposes the EU Energy Performance of Buildings Directive (EPBD), and the German lighting control duty in Section 56(6) derives from Article 13(12) EPBD. For the differences, see EPBD Article 13 in Germany and the EU.
The German rule covers the same buildings as the building automation duty in Section 56(1):
- Non-residential buildings with a heating system, an air-conditioning system or a combined heating/air-conditioning and ventilation system with a rated output of more than 70 kW.
- The threshold applies per system, not per tenant and not per part of the building.
- The responsible party is the developer or owner (Section 8 GModG). In let buildings, this is usually the landlord.
The trigger is the heating or air-conditioning system, not the lighting load. Once the threshold is exceeded, the lighting is fully part of the obligation. How to check the threshold for your building is explained in Am I affected? The 70 kW threshold.
What do sentence 1 and sentence 2 require?
Sentence 1: the mandatory duty
Sentence 1 leaves no room for interpretation. Buildings in scope must be equipped with automatic lighting control by 31 December 2029.
Sentence 2: the "should" requirement
Sentence 2 adds that the control should be appropriately zoned and include occupancy detection. The legislative reasoning is in BT-Drs. 21/7009.
Reading "should" (soll) as optional is a mistake. In German administrative law, a "should" provision describes the default case. Departures are allowed only in atypical, justifiable cases. In addition, the EPBD phrases zoning and occupancy detection as "shall", that is, as mandatory. Plan zones and presence or motion detection as standard; see Zoning and occupancy detection.
Occupancy detection is compatible with workplace rules. Under EN 12464-1:2021 and the German workplace rule ASR A3.4, the minimum illuminance must be reached whenever people are present. Background lighting during absence is a separate matter. In practice, the control dims to a low background level when an area is empty and may switch off later.
Which exemptions does the law allow?
Section 56(1) and (6) contain the same exemption. The obligation does not apply where installation is technically impossible or economically unreasonable. The benchmark is the economic efficiency principle in Section 5 GModG, and exemptions are governed by Section 102. Paraphrased, the core idea is that the expenditure must be recoverable through savings within the usual service life. The precise assessment is made case by case.
For lighting control, this exemption rarely applies. The LBNL meta-analysis (Williams et al., LEUKOS 2012, 240 values from 88 studies) found average savings of 24 % from occupancy-based control alone and 38 % for combinations of strategies. Project values in sparsely occupied halls are often higher. Details: Exemption: economically unreasonable.
What does paragraph 6 explicitly not require?
New luminaires are not required. What is required is automatic control. If you already operate LED luminaires with dimmable drivers (0-10 V or DALI), control can usually be retrofitted. With a wireless system such as Bluetooth Mesh, no new control cabling is needed. Where the driver has no 12 V auxiliary output (AUX), hall sensors with their own power supply and relay are available. In offices, whether a driver replacement makes sense is assessed case by case. See Retrofitting lighting control on existing luminaires.
How does paragraph 6 relate to building automation under paragraph 1?
Section 56(1) requires the same buildings to have building automation by 31 December 2029, with the functions listed in paragraph 2, including monitoring, logging, analysis and open interfaces. Lighting control under paragraph 6 is a separate duty alongside it. The two are linked: under Section 3 GModG, lighting is a technical building system, and presence and light sensors supply data the building automation can use. With SensMotion, the monitoring platform passes this data to the building automation via BACnet/IP.
Lighting control covers paragraph 6 and supports paragraph 1, but it does not replace automation for heating, ventilation and air conditioning. For building automation already installed, paragraph 4 contains a transitional rule: systems installed up to three years before 1 January 2027 are given ten years to be upgraded. Details are in the Act.
Is there a fine for missing lighting control?
Section 108 GModG provides for fines of up to EUR 5,000 for breaches of Section 56(1), the building automation duty. The wording does not specify a fine for paragraph 6. That does not make the lighting duty any less binding:
- The obligation applies whether or not a fine is attached.
- It can become relevant in leases, in acquisitions and due diligence, in ESG reporting and in financing.
- Under Section 3 GModG, lighting is a technical building system.
- The sensors supply data for the building automation under paragraph 1, where a breach can be fined.
What should you do now?
- Check the threshold: establish the rated output of each heating, air-conditioning or combined system, for example with the obligation check.
- Survey the existing installation: luminaire types, drivers (0-10 V, DALI, AUX output), mounting heights and operating hours per area.
- Plan zones and occupancy detection: design detection areas from manufacturer coverage diagrams rather than generic radii.
- Measure the baseline: only a measurement before the retrofit lets you verify savings later over the same reference period.
- Clarify interfaces: plan lighting control and building automation under paragraph 1 together.
- Allow lead time, especially across several sites.
Frequently asked questions
Is zoning mandatory or only recommended?
Section 56(6) sentence 2 GModG phrases zoning and occupancy detection as "should". In German administrative law, that is the default case, and departures need an atypical, justifiable situation. The EPBD even makes both mandatory.
Do I have to replace my luminaires?
No. The law requires automatic control, not new luminaires. Existing LED luminaires with dimmable drivers (0-10 V or DALI) can usually be retrofitted.
Who is responsible, the owner or the tenant?
Under Section 8 GModG, the developer or owner is responsible. In let buildings, this is usually the landlord. The lease can set out how costs are shared.
What if the system is rated at exactly 70 kW?
The wording refers to a rated output of more than 70 kW. What counts is the output per system. Which generators are added together is explained in our 70 kW threshold article.
Does lighting control satisfy all of Section 56?
No. Lighting control covers the lighting duty under paragraph 6 and can supply data to building automation. Building automation for heating, ventilation and air conditioning under paragraphs 1 and 2 is a separate part of the obligation.
Last reviewed: 18 November 2026. General information, not legal advice. The legal text is authoritative.