- New luminaires
- not required, automatic control is what counts (§ 56(6) GModG, Germany)
- Deadline for buildings above 70 kW
- 31.12.2029 (§ 56(6) sentence 1 GModG)
- Prerequisite
- LED luminaire with dimmable driver, 0-10 V or DALI (system requirement)
- No 12 V auxiliary output in halls
- EFS104 with its own power supply and relay (system solution)
- Wireless network
- Bluetooth Mesh, CR05 gateway for up to 100 nodes (manufacturer data)
- Data hand-over
- BACnet/IP to the building automation system (AU-Manager)
Does the lighting control obligation mean new luminaires?
No. Under § 56(6) of the GModG (German Building Modernisation Act, Gebäudemodernisierungsgesetz), non-residential buildings above 70 kW must have automatic lighting control by 31 December 2029. New luminaires are not required. The control should be appropriately zoned and include occupancy detection. What this means is explained in our article on § 56(6) GModG. Many halls and offices have already switched to LED in recent years. Those luminaires stay where they are and are supplemented with sensors and lighting management.
Which luminaires can be retrofitted?
LED luminaires with a dimmable driver can be retrofitted. The driver (control gear) must accept a control signal, either analogue via 0-10 V or digital via DALI. Only then can the control system dim the luminaire, lower it to background level and regulate it according to daylight.
How do I read the type plate?
What matters is the label on the driver, not just the one on the luminaire. On high-bay luminaires the driver is often mounted on the outside of the housing; on office luminaires it sits behind the cover.
- DALI: marked "DALI" or "DALI-2", control terminals usually labelled "DA".
- 0-10 V: marked "0-10 V" or "DIM", terminals labelled "DIM+" and "DIM–" or "+" and "–".
- Auxiliary output: marked "AUX" with "12 V". A sensor can be powered directly from the driver through it.
- Not dimmable: only mains terminals (L, N, PE) and the LED output, no control terminals.
If the label shows something different, such as "1-10 V", or is illegible, the data sheet for the type number helps. A check on site gives the final answer.
AUX output or EFS104: how is the sensor powered?
If the driver has a 12 V auxiliary output (AUX), it also powers the sensor. This is the leanest solution.
If there is no AUX output, that is not an obstacle in halls. There the EFS104 is used, a high-bay sensor with its own power supply and relay for mounting heights of 6 to 15 m. In offices the right solution is checked case by case, which may mean replacing the driver. Replacing a driver is a much smaller intervention than replacing a luminaire. An overview of the sensors is available under products.
Wireless or cabling: what makes sense in existing buildings?
A wired control system, such as a DALI bus, needs its own control cables to every luminaire. In an existing building that means new cable routes, work on ceilings and cable trays, and often interruptions to operations. In new construction, where cabling can be planned from the start, wired systems have their place.
In existing buildings, wireless control over Bluetooth Mesh is usually the better choice. Each node can pass messages on, so the network grows with the installation. New control cables are not needed; the luminaire only needs its existing power supply. For locations without a power connection, battery-powered sensors such as the BCS107 are available. One CR05 gateway connects up to 100 nodes. Larger installations get several gateways accordingly, with their positions fixed during planning.
The objection that wireless is unsuitable for building automation does not hold: the AU-Manager (Autani EnergyCenter) provides monitoring and passes data to the building automation system via BACnet/IP. Building automation for heating, ventilation and air-conditioning under § 56(1) and (2) remains a separate part of the obligation.
How does a retrofit project run?
A retrofit usually follows five steps:
- Survey on site: luminaires, drivers and type plates, mounting heights, use, operating hours and daylight situation.
- 3D planning: the floor plan becomes a 3D model. People and forklifts are simulated, and detection areas follow the manufacturer's diagrams rather than flat radii. This produces the zoning before any sensor is mounted. SensMotion uses its own planning software for this, see 3D planning.
- Installation during operation: section by section, luminaire by luminaire.
- Commissioning: setting zones, hold times, background light and daylight control, testing the function and documenting it.
- Monitoring: consumption and switching behaviour are recorded continuously per zone. This is the basis for verifying the savings later on.
How zones are sensibly divided for each building type is described in our article on zoning and occupancy detection.
What if the luminaires are fluorescent or old?
The retrofit requires dimmable LED drivers. Fluorescent lamps, metal halide lamps or LED luminaires with non-dimmable drivers cannot be controlled this way. In that case, converting to LED comes first.
This is not a detour but an opportunity: if you are renewing anyway, choose dimmable drivers with 0-10 V or DALI, ideally with a 12 V auxiliary output. Luminaire replacement and controls can then be planned together, and the savings of both measures complement each other. With conversion kits, check that they are dimmable. Not every LED replacement tube is.
How long are operations interrupted, and who installs?
A complete shutdown is usually not necessary. Installation takes place section by section while the building is in use. Only the luminaire or circuit being worked on is disconnected at any one time. In halls, mobile elevating work platforms are needed, so the work can be scheduled for quieter periods or for areas that are not in use.
Installation and commissioning are usually carried out by SensMotion. If you prefer, your own electrical contractor installs according to our plan. Work on the 230 V mains must in any case be done by qualified electricians. Monitoring is included in every project, and a maintenance and energy management contract is available as an option.
Frequently asked questions
Can I check myself whether my luminaires can be retrofitted?
A first look at the driver's type plate often tells you. If it says DALI or 0-10 V and there are control terminals, a retrofit is likely possible. If the information is missing, the data sheet for the type number helps. The on-site check is what counts.
What happens if my driver has no AUX output?
In halls, the EFS104 with its own power supply and relay is used. In offices, the right solution is checked, possibly including a driver replacement. Replacing the luminaire is not necessary for this.
Do I need new cables?
No new control cables are needed, because sensors and luminaires communicate over Bluetooth Mesh. The existing power supply to the luminaires continues to be used. Where there is no power connection, battery-powered sensors are an option.
Can the wireless solution be connected to building automation?
Yes. The AU-Manager passes data to the building automation system via BACnet/IP. The lighting control therefore covers lighting under § 56(6) and supplies data for building automation. Automation of heating, ventilation and air-conditioning is a separate part.
Do operations have to stop during installation?
Usually not. Installation is carried out in sections, and only the luminaire or circuit being worked on is briefly disconnected. The sections are agreed with you in advance.