What has been published?
The act of 23 July 2026 was promulgated in the Federal Law Gazette, BGBl. 2026 I No. 226, issued on 28 July 2026. Under Article 9(1), it comes into force on the day after promulgation, that is 29 July 2026. Further parts follow on 1 January 2027, 1 January 2028 and 1 January 2030. Article 1 renames the Building Energy Act as the GModG (German Building Modernisation Act, Gebäudemodernisierungsgesetz, sometimes abbreviated GMG). The act also transposes the EU Energy Performance of Buildings Directive (EPBD).
What does Section 56(6) require?
Article 1 rewrites Section 56. Paragraph 6 introduces a lighting control obligation for the first time. In substance: in addition to the requirements of paragraph 2, a non-residential building whose system under paragraph 1 has a rated output of more than 70 kW must be equipped with automatic lighting control by the end of 31 December 2029, unless this is technically impossible or economically unreasonable.
Sentence 2 adds that the control should be appropriately zoned and include occupancy detection. In German administrative law, a "should" provision is the rule, and departures are only allowed in atypical cases that can be justified. The threshold refers to the rated output of a heating, air-conditioning or combined system, not lighting load; once it is exceeded, lighting is covered. The law does not require new luminaires. Whether your building is affected is covered in the 70 kW threshold.
And building automation?
Section 56(1) requires the same buildings to have a building automation and control system by 31 December 2029, with the functions listed in paragraph 2, such as continuous monitoring, logging and analysis of energy use and an open, freely configurable interface. Section 108 provides for a fine of up to EUR 5,000 for breaches of paragraph 1. The wording names no fine for paragraph 6. The obligation still applies and can become relevant in leases, due diligence, ESG reporting and financing.
What has changed compared with the GEG?
The former Section 71a GEG has been absorbed into Section 56. The threshold for building automation falls to 70 kW, and lighting control is added as a separate obligation. The differences are set out in GEG Section 71a vs GModG Section 56, and the complete wording in Section 56 GModG full text.
What does this mean for owners?
Responsibility lies with the owner, and for let buildings usually the landlord. A little over three years remain for survey, planning, installation and commissioning, with less margin for multi-site portfolios. What paragraph 6 means in detail is explained in Section 56(6) GModG explained. This news item is not legal advice; the statutory text is authoritative.
Source
General information, not legal advice. The legal text is authoritative.